Seattle Tunnel Project: World-Record Drill
One reminder about the volatility of local politics is the project to replace the Alaska Way Vidaduct running alongside Puget Sound in Seattle. The structure was critically damaged in the 2001 Nisqually Earthquake, and locals needed eight years to figure out what to do about that.
Nonetheless, they finally figured it out, and the answer is a $4.25 billion tunnel project through problematic ground.
Key to the tunnel project is this behemoth:
Mike Lindblom of The Seattle Times explains:


Top: The cutting head for the drill that will bore the tunnel.
Bottom: The rotary joint will spin the cutting head at about 3 RPM.
Setting aside the political malady this project has been, the Washington State Department of Transportation and its contractors are about to embark on one of the most ridiculously amazing construction projects ever witnessed. And the sad thing is if they manage to pull this off, they won't be doing anything to reduce traffic volume in the downtown grid.
Still, this will be a feat—or disaster—to behold.
____________________
Notes:
Lindblom, Mike. "Work nearly complete on assembling Highway 99 tunnel drill". The Seattle Times. November 22, 2012. SeattleTimes.com. November 22, 2012. http://seattletimes.com/html/localnews/2019744178_boringmachine23m.html
One reminder about the volatility of local politics is the project to replace the Alaska Way Vidaduct running alongside Puget Sound in Seattle. The structure was critically damaged in the 2001 Nisqually Earthquake, and locals needed eight years to figure out what to do about that.
Nonetheless, they finally figured it out, and the answer is a $4.25 billion tunnel project through problematic ground.
Key to the tunnel project is this behemoth:
Mike Lindblom of The Seattle Times explains:
Workers in Osaka, Japan, are almost done assembling the world-record, 57.5-foot diameter drill that will churn beneath downtown Seattle next year, to form the Highway 99 tunnel.
On Nov. 29, the giant cutter head will be hoisted and attached to the front of the cylindrical machine, longer than a football field. The team at Hitachi-Zosen will test the machine before the Washington State Department of Transportation formally accepts it at a ceremony in December.
Construction of the drill is on schedule, said Chris Dixon, project director for Seattle Tunnel Partners.
The drill will be dismantled into 41 sections and shipped to Seattle's Terminal 46 in March. Crews here will lower the parts into a huge pit in Sodo. Drilling of the two-mile tunnel is scheduled to start in June.
The first few months will be the trickiest, as the machine crawls through weak fill soil, then beneath the old Alaskan Way Viaduct and Pioneer Square's brick buildings. Hundreds of concrete pillars are being poured to create buried walls on either side of the machine's path, to reduce vibration risks nearby.
Breakthrough is scheduled at South Lake Union by October 2014, with traffic to use the four-lane toll tunnel by the start of 2016.
On Nov. 29, the giant cutter head will be hoisted and attached to the front of the cylindrical machine, longer than a football field. The team at Hitachi-Zosen will test the machine before the Washington State Department of Transportation formally accepts it at a ceremony in December.
Construction of the drill is on schedule, said Chris Dixon, project director for Seattle Tunnel Partners.
The drill will be dismantled into 41 sections and shipped to Seattle's Terminal 46 in March. Crews here will lower the parts into a huge pit in Sodo. Drilling of the two-mile tunnel is scheduled to start in June.
The first few months will be the trickiest, as the machine crawls through weak fill soil, then beneath the old Alaskan Way Viaduct and Pioneer Square's brick buildings. Hundreds of concrete pillars are being poured to create buried walls on either side of the machine's path, to reduce vibration risks nearby.
Breakthrough is scheduled at South Lake Union by October 2014, with traffic to use the four-lane toll tunnel by the start of 2016.


Top: The cutting head for the drill that will bore the tunnel.
Bottom: The rotary joint will spin the cutting head at about 3 RPM.
Setting aside the political malady this project has been, the Washington State Department of Transportation and its contractors are about to embark on one of the most ridiculously amazing construction projects ever witnessed. And the sad thing is if they manage to pull this off, they won't be doing anything to reduce traffic volume in the downtown grid.
Still, this will be a feat—or disaster—to behold.
____________________
Notes:
Lindblom, Mike. "Work nearly complete on assembling Highway 99 tunnel drill". The Seattle Times. November 22, 2012. SeattleTimes.com. November 22, 2012. http://seattletimes.com/html/localnews/2019744178_boringmachine23m.html



